A public consensus has formed on Vietnam’s need to invest in nuclear power, though many questions were not answered in the investment report. Tien Phong raised some of these in a recent interview.
![]() |
Mr. Vuong Huu Tan. |
The nation’s first nuclear power project will be debated and almost certainly approved during the National Assembly’s autumn session. Vuong Huu Tan, director of the Vietnam Atomic Energy Institute, talked with Tien Phong newspaper about this great project.
Tan says the first unit of the nuclear power plant will go into service in 2020. Construction of the first turbine will begin in 2014 or 2015. Thus
The investor of the first nuclear power projects is the state power monopoly, Electricity of Vietnam (EVN). Two separate plants are planned to be built on the coast of The first plant will be based in Phuoc Dinh commune, Ninh Phuoc district and the second in Vinh Hai commune, Ninh Hai district. The two first nuclear power plants will have a total capacity of 4000 MW. Each plant will cover 400 hectares. The capacity of the largest power plant in |
Tien Phong: US$12 billion is a huge amount of money, about 13 percent of the country’s current annual gross domestic product (GDP). Is it necessary to invest that money to build a nuclear power plant when
Tan: The investment capital in the first nuclear power plant will be $12 billion assuming the Incremental Capital – Output Rate (ICOR) is $3000/KW. Certainly we have to absolutely exploit hydropower because it is a renewable source of power. But after the Son La hydropower project, we hardly have any more sites suitable for big hydropower projects.
TP: How is the rate of return on nuclear power compared to hydro and thermal-power?
Tan: Nuclear power can compete with power produced from imported coal, oil or gas. In the long run, the advantage of nuclear power is that the expenditure for operation and maintenance is low, less than 25 percent of the cost price of power compared to 60 to70 percent for thermal power.
Once investment costs are paid back, nuclear power is the cheapest. The lifespan of nuclear power plants is very long. The new reactor designs can operate for 60-80 years. Investors can recover their investment within 20 years and then they only have to maintain nuclear power plants for the next 60 years.
When we put two turbines into operation, each with a capacity of 1000 megawatts (MW), we will have only 6-7 billion kilowatt-hours (KWh) a year. Meanwhile,
TP: How will we run the first nuclear power plant? Don’t we lack human resources in this sector?
Tan: That is the common problem of countries when they begin building their first nuclear power plants. We will build the plant while training staff. For example, we only need to train workers to run the nuclear power plants two years before the plant is put into operation. If we train them right now, they will be unemployed.
We are working on a decree to implement the Law on Atomic Energy that emphasizes steps to secure human resources for this sector. I hope that before year’s end the Government will approve that decree.
TP: How many staff are enough for the first nuclear power plant?
Tan: Many for the whole project, but not so many for the nuclear part. For example, a plant with two turbines needs around 800-1000 workers but only 10-20 percent of them are nuclear technology specialists. The nuclear safety agency needs around 80-100 people.
Ta Van Huong, head of the Energy Department at the Ministry of Industry and Trade, explains that “according to “There is a foreign relations element. We have to consider political, social and cultural relationships and traditional cooperation in choosing our provider of nuclear technology. “Financial assistance to |
TP: What about safety?
Tan: Because of accidents like
TP: What will we do with nuclear waste?
Tan: This is a world-wide concern. We will import nuclear technology and radioactive waste treatment technology from the same source. For low and medium-level nuclear waste, the treatment technology has been popularized and commercialized. It is safe and used by many countries.
Highly radioactive waste, the spent fuel rods, can be reprocessed into new fuel. Recycling this kind of waste is a highly sensitive issue because it can also be converted into weapons. Thus its disposition will be strictly controlled by the International Atomic Energy Agency (IAEA).
Masahiro Yagi, director of
TP: How have we prepared the legal foundation for the first nuclear power plant?

The future nuclear power plant of Vietnam.
Tan: In June, 2008, the National Assembly approved the Fundamental Law on Atomic Energy in
The first decree will guide the implementation of some articles about nuclear power. The second is about nuclear power plants. The third will establish administrative penalties in the nuclear power sector. There are also decrees of the Prime Minister and ministerial circulars relating to the project.
TP: What technology will we choose for our first nuclear power plant?
Tan: There are three major types of reactors: boiling water reactor, pressurized water reactor and heavy water reactor.
We will choose the most modern technology currently available, so-called third or third-plus generation reactors, to ensure safety and economic effectiveness.
TP: Have we scrutinized possible contractors?
Tan: We’re not tilting to any country yet. Japan offers an innovative pressurized water reactor design,
TP: Will we have to import fuel for this plant?
Tan: Yes, absolutely. In the long run, when we have enough nuclear power plants, we will consider the construction of a processing plant. We will import uranium to process into fuel bars.
TP: But
Tan: According to initial surveys,
Since nuclear power was first given serious consideration, its projected cost has risen from $1500-1700 to $3500-3800 per kilo hour (KWh), said Ta Van Huong, director of the Energy Department under the Ministry of Industry and Trade at a Vietnam-China workshop on nuclear power on October 15. At that cost per kilowatt hour, investment capital in each 1000 megawatt turbine will reach three to four billion dollars, three times the cost of an thermal power plant of the same scale. This is only estimation but the increase of investment cost is now a big challenge for However, some officials still affirm that nuclear power plants will be cost-effective. Nguyen Hoai In “In the years to come, thermal-power will account for a big part of |
Related news:
- Russia to build Vietnam’s first nuclear power plant
- Safety will be paramount at Vietnam’s first nuclear power plant
- Nuclear power plant: The cheapest does not always mean the best
- Government establishes nuclear power steering board
- VND3 trillion project for nuclear power gets a go-ahead